|
-
Reduce Vehicle Operating Costs
-
Reduce Travel Time
-
Increased road Safety
-
Improved Institutional Standards
-
Better capacity to manage Road
Network
-
Initiation of PPP Projects
-
Long term maintenance strategy with
performance based/output based contracts.
-
Increased Social issues.
-
Environmental friendly construction
activities
Major components of
the Project
i)
Up-gradation
and Improvement component for 429 Kms. (2 lanes and 4 lanes)
Rs. 1545.61 Cr.
ii)
Long Term
Performance Based Maintenance Contracts (LTPBMC) for 6241 Kms.
Rs. 1427.66 Cr.
iii)
Institutional
Strengthening, Road Safety & PPP Facilitation Support
etc., Rs. 191.40 Cr.
Cost and Duration of the
Project:
Cost of the project is estimated at Rs.
3165.00 Cr. (@ Rs. 49.00 per dollar). Project duration 5 years
from signing of loan agreement (2010-2015)
Up-gradation and
Improvement component for 429 Kms.
List of
Roads
Phase-I
Kms
Estimated Cost
Rs. in Cr.
Packages
-
Chittoor-Puttur road(CP-01)
-
60.80
150.73
-
Kandi-Shadnagar road (KS-05) -
69.90
247.65
-
Kurnool-Devanakonda road (KD-02)
-
60.60
102.01
-
Mydukur-Jammalamadugu road - 35.67
172.10
(MJ-03 &
MJ-04)
-
Jagityal-Peddapalli road
(JP-06)
-
57.80
113.18
(G.O. Ms. No. 168, T(R&B)
(R.IV),
Dt: 24.07.2009 for packages 1 to
5)
Phase-II
Probable Cost
6.
Pedana-Vissannapeta road
-
82.90
320.00 7.
Kakinada-Rajahmundry road
-
61.60
319.00
A.
Works:
Ø
Package-I, - Agreement
Concluded on 12.08.2009 and Work is in
progress.
Ø
For Packages KD-02,
MJ-03, MJ-04 & KS-05, Re-invitation of bids is under
progress.
Ø
For package 5,
Agreement concluded on 26.03.2010 and preparatory works are in
progress.
Ø
For package 6 & 7
DPRs under finalisation.
Ø
Contractor's Workshop was Conducted on 29.07.2010.
B.
Services:
Ø
M/s Scott Wilson Ltd.,
U.K.
Joint Venture
with M/s. Scott Wilson India. Pvt. Ltd., are appointed as
Construction Supervision consultants for packages CP-01,
MJ-03, MJ-04, KS-05 & JP-06 (Click Here)
Long Term Performance
Based Maintenance Contracts (LTPBMC) for 6241 Kms
(Click here
)
Ø
Total No. of packages &
length: 37
packages
6241
Kms length.
Ø
No. of entrusted
packages & length:
Entrusted
packages 11 Nos. (G.O. Ms. No. 16, T(R&B)
(R.IV),
2013 Kms length Dt: 19.01.2009 for 13
packages, Rs. 410.00
Crores).
Ø
11 packages are
grounded.
Works are in Progress
Ø
For balance packages
of 26 Nos., length 4228 Kms,
tenders are programmed to be called for, during July - August
2010.
INSTITUTIONAL
STRENGTHENING:
In
the Project Appraisal Document (PAD) the amount provided for Institutional
Strengthening is (a) Rs. 4.20 US $ Million for ISAP implementation, (b) Rs.
1.80 US $ Million for Training and (c) Rs. 3.36 US $ Million for Monitoring
& Facilitation (ISAP & GAAP).
This
component will provide targeted technical assistance, training and advisory
services for (a) operationalization of the APRDC, with requisite capacity for
its responsibilities in managing the CRN and new PPP Projects; and (b) various
aspects of project implementation including the Asset management Program, the
Governance and Accountability Action Plan (GAAP) and the Institutional
Strengthening Action Plan (ISAP), plus associated monitoring and coordination.
PPP
Projects under Implementation:
Ø
Second bridge across river Godavari near
Rajahmundry
including approach roads connecting East & West Godavari Districts. – Total
Project Cost of Rs. 808.00 Cr. -
Length in Kms - Bridge 4.20 km approaches 11 KM - Concession period 25 years.
Ø
Hyderabad
- Karimnagar -
Ramagundam Road
(Rajiv Rahadari). – Length in Kms – 207 Kms. – Total Project cost of Rs.1358.19
Cr. - Concession period – 25
years.
Ø
Narketpally - Addanki -
Medaramitla
Road
. – Length in Kms – 213 Kms. – Total Project cost of Rs. 1196.84
Cr. – Concession period – 24 years.
PPP Projects under Pipe
Line:
1.
Puthalapattu -
Naidupet
Road
from Km 59/0 to 116.83. Length in Kms – 58 Kms. – Total Project cost of Rs.
306.00 Cr.
2.
Up-gradation and Improvement of road from
Nellore
to
Gooty
Road
via Badvel – Mydukur – Rayalacheruvu. Length in Kms – 194 Kms. Total Project
cost of Rs. 962.00 Cr.
3.
Up-gradation of road from Anakapalli to Anandapuram (SH-38) via Sabbavaram. Length in Kms – 48
Kms. Total Project cost of Rs. 455.00 Cr.
4.
Up-gradation of road Gundugolanu - Devarapalli - Kovveru. Length in Kms – 68 Kms. Total
Project cost of Rs. 531.00 Cr.
ANNUITY PROJECTS:
(Works
in Progress)
1.
Improvements to Pulivendula –
Ambakapalli – Murarichintala Road from Km 5/2 to 16/0 in Kadapa
District.-Est. Cost of Rs. 22.40 Cr.
2.
Improvement to Pulivendula –
Ramireddypalli –
Palagiri
Road
from Km 2/5
to 27/6 in Kadapa District. - Est. Cost of Rs. 32.30
Cr.
3.
Improvements to Pulivendula –
Parnapalli Road
from Km 4/0 to 20/0 and 27/0
to 31/5 in Kadapa District. -Est. Cost of Rs. 28.91
Cr.
4.
Improvements to Rayalapyuram –
Gandluru Road
from Km 12/0 to 28/0 in Kadapa
District. -Est. Cost of Rs. 20.45 Cr.
5.
Improvements to Pulivendula –
Alavalapadu –
Vempally Road
from km 7/0
to 14/440 and 19/2 to 31/6 in Kadapa District. -Est. Cost of
Rs. 28.50 Cr.
6.
Up-gradation & improvement of
Kadapa - Pulivendula road in Kadapa District. – Total Est.
Cost of Rs. 297.00 Cr.
i)
(KP-01)
from km 1/700 to 15/00. – Rs. 67.05 Cr
ii)
(KP-02)
from km 15/00 to 28/00. – Rs. 55.15 Cr
iii)
(KP-03)
from km 28/00 to 46/200. – Rs. 91.46 Cr
iv)
(KP-04)
from km 46/200 to 67/600 – Rs. 76.61 Cr
Project
under Annuity:
Ø
Construction of bridge across Vasista
branch of river
Godavari at
Narsapur connecting Narsapur of West Godavari District with
Sakhinetipalli of East Godavari District. – Project Cost of
Rs. 66.57 Cr. Concession period – 12
years.
Core Network Roads -- Maintenance
Policy
The Periodic Maintenance and emergency
works pertaining to core network roads are sanctioned as per
norms and tenders are under process, and certain works are in
progress. The Ordinary Maintenance work are in progress.
Maintenance and Management of Core net
roads
Annual Maintenance and Periodic
Maintenance of these roads is done through the budget support
of A.P Government under maintenance grant.
3054: SH-18.
Any
capital nature of works viz, Road Widening, Reconstruction of
Bridges, CC Pavements works etc, of these core net roads are
executed through the Budget support of Government of A.P.
under APRDC-grant (Non-Plan).
3054: SH-14.
These
works are procured through E plat form executed through the
Contract system and monitored through the net work of
Territorial Engineering staff of RBD.
|